Weekly Update: March 9, 2020

  • by
weekly update

March 9, 2020
Michael Yee
Hawaii County Planning Department
101 Pauahi Street, Ste. 3
Hilo, HI 96720

SUBJECT: PUNA GEOTHERMAL VENTURE (PGV) SITE ACTIVITIES

Dear Mr. Yee:

Pursuant to Condition No. 4 of the Geothermal Resource Permit, Puna Geothermal Venture (PGV) hereby submits the Weekly Status Report for the week ending March 8, 2020.

Power plant

Continued with turbine and generator overhauls.

  • OEC 11 continued power skid equipment installation.
  • OEC 22 continued power skid equipment installation.
  • OEC 25 continued power skid equipment installation.

Continued electrical substation installation.

Wellfield

  • KS-14 Well maintenance will continue when Rig 4 is available.
  • KS-17 Continued ground preparation for drill rig operation.
  • KS-18 Drilling is delayed due to equipment issues.
  • MW-5 Drilling postponed, relocating Rig #4 to KS-17.
  • MW-4 Continued of pump operations.

If you have any questions, please do not hesitate to call me.

Sincerely,

Ronald P. Quesada
EH&S Manager